Maygrove Road closure starts

It was pushed back a few days, but the partial closure of Maygrove Road for three months has now begun. The recriminations over the lack of notice for residents and councillors continue however.

MaygroveRd_closure

We reported last week the sudden annoucement of this lengthy road closure. So many people were up in arms about the lack of notice that the start date was moved from last Monday to yesterday. Today the road was definitively closed. To recap, the closure is from Ariel Road to 80 Maygrove Road. For the time being, the pavement is open on both sides, though residents should expect the northside pavement to close.

MaygroveRd_closure_eastbound

Here’s how Camden’s Brian Foxton, Network Manager, explained the snafu:

“A temporary traffic restriction order (closure) was applied for in December 2013 however the payments were not made until after the New Year’s break. While “approving” the order in principle we do not advertise until all payments etc have been made. The order was duly advertised, in compliance with the Road Traffic Regulations, on two separate occasions in the Ham & High on the 16th & 23rd January 2014. We do note however that not all Camden residents have access to this or wish to acquire a copy.

The Construction Management Plan for the development does state that there would be a potential road closure to carry out the sewer works however as the discussions progressed ward councillors and residents should have been kept informed and I can only apologise that this was not the case…. We are reviewing processes to ensure this does not reoccur.

…[t]he contractors… are going to ensure that a “filter” lane is provided to allow properties to be accessed in terms of disabled or physically impaired residents, in addition to any deliveries which may be required.

There should also now be a weekly newsletter for residents.