More noise as Network Rail to clear vegetation overnight

Residents near The Black Path, which runs along side the northern side of the Thameslink line, may find it’s not just the warm weather keeping them awake at night next week.

Network Rail is going to be removing vegetation along the track behind Sumatra Road and Ravenshaw Street between 11pm and 5.30am from Monday to Friday and the work will apparently involve the use of chainsaws, flail machines, chipping machines or handsaws – so it could get a bit noisy!

Thameslink_foliage

It’s not clear why the work all has to take place overnight or whether it requires five full nights of work. Perhaps one of our new West Hampstead councillors could look into this, and ensure National Rail does indeed have all the correct permits for this after-hours work.

Local residents were sent a circular alerting them to the potential disruption, and are advised to call the 24-hour national helpline on 08457 114141 if they have any concerns, though it seems unlikley that that’s going to stop any noise then and there.

Residents may find it’s a long week as some are also likely to be disturbed by the more extensive Overgound construction work taking place on Sunday night. The Ivory Coast vs Japan World Cup match, whicj kicks off at 2am Sunday morning, might have a disproportionately high number of viewers in NW6.

Overground works to cause Sunday noise disruption

As part of the work to rebuild West Hampstead Overground station, the platforms need to be extended and widened and, unfortunately, this means it’s going to get noisy – starting this Sunday.

For locals who live very near the station it’s likely to be uncomfortable at times. Work is scheduled to start at 12.30am on Sunday (yes, as in just after midnight on Saturday) and run right through to 8pm. “The exact finish times will vary and on occasion will continue into the following Monday, however the majority of work will be completed by 20:00 on Sunday evenings.”

There will be some pile driving work during this time and, as anyone who’s lived through pile driving will tell you, that can be hard to live with. TfL tell me that the loudest pile driving will actually be in the initial phases as they need to drive the piles on which the rig for the rest of the pile driving will sit. Still with me? The good news, such as it is, is therefore that when you think that it can’t get any louder, you’ll actually be right.

TfL’s Director for London Overground, Mike Stubbs, told West Hampstead Life:

“We always seek to undertake work in a way that causes the minimum disruption and inconvenience possible to residents near to the railway, however, despite our best efforts some work will unavoidably need to be carried out overnight. We will be monitoring the works at West Hampstead carefully to minimise disturbance, and any local residents who feel that there is disturbance, or would like more information, can contact us 24 hours a day on our helpline on 0343 222 7878.”

TfL is naturally wary of setting out a very strict timetable of works as the situation can change very quickly on a project of this nature. Note that although it doesn’t expect to be carrying out noisy works in the middle of the night, it is not categorically ruling it out either.

What this boils down to is that noisy work will be carried out on Sundays during the day and there will be some occasional disruption during the nights as well. Additional work will take place during the rest of the week from 7am-7pm though even then, “There may be some occasions when we need to work at night , however this will be restricted to quiet activities that should not affect neighbouring properties. If any night work is likely to cause disturbance, we will notify you in advance. Any additional lighting required for overnight works will be directed away from nearby residential property and dust will be dampened down on site.”

For those of you interested in the specifics of the construction, Tfl is installing a retaining wall in the slopes at the back of the platforms, and doing some excavation work using heavy machinery to build foundations for the new extensions. Blockwork will be built up to create the new sections of platform and new surfacing will be laid. Additional CCTV cameras, speakers and lighting will be installed on the new platforms.

Obviously, the Overground line will be closed through West Hampstead on Sundays when the work is carrying out, so don’t expect to be catching the train to Richmond on a Sunday anytime soon although you can catch the new special Sunday service from Stratford to Willesden Junction via South Hampstead or Kilburn High Road station and change there. The new longer trains, which are necessitating this work, will be introduced by the end of 2015.

Earplugs are available from most chemists.